Build Timeline & Roles Simulator

Aligns the ~52-week station contract with volunteer roles. Shows when each role is needed and network-wide demand while sites are still under construction and crafts keep flying.

52-week programme bar

P1
P2
P3
P4
P5
P6
P7

P1 Mobilisation → P3 Temporary power (first revenue) → P7 Full ops handover

Phase timeline ↔ volunteer roles

P1 — Mobilisation & site survey

Weeks 1–4

Deliverables: Survey report, HSE plan, Temporary fence, Works notices

RolePer station (contract)Network demand now*
Contract Administrator 1 308
HSE Build Officer 1 308
Community Liaison (Build) 1 308
Site Engineer (Pad & Structures) 1 308

* 308 contracts currently in this phase · ~1232 volunteer seats required network-wide for this phase alone

P2 — Civil works — pad foundation

Weeks 5–14

Deliverables: Excavation, Foundations, Primary pad slab, Drainage

RolePer station (contract)Network demand now*
Site Engineer (Pad & Structures) 2 618
Materials & Logistics Coordinator 2 618
HSE Build Officer 2 618
Site Build Volunteer 4 1236
Contract Administrator 1 309

* 309 contracts currently in this phase · ~3399 volunteer seats required network-wide for this phase alone

P3 — Temporary power & limited ops enablement

Weeks 15–20

Deliverables: Temporary charge kits, Earth grid, Ops demarcation, First revenue-capable pad

RolePer station (contract)Network demand now*
Power Systems Technician 2 618
Charge Technician 2 618
Safety & Anti-Collision Observer 1 309
HSE Build Officer 1 309
Operations Lead 1 309

* 309 contracts currently in this phase · ~2163 volunteer seats required network-wide for this phase alone

P4 — Superstructure — shelter & services core

Weeks 21–32

Deliverables: Shelter frame, Roof, Restroom shell, Store room

RolePer station (contract)Network demand now*
Site Engineer (Pad & Structures) 2 618
Site Build Volunteer 5 1545
Materials & Logistics Coordinator 2 618
HSE Build Officer 2 618
Contract Administrator 1 309

* 309 contracts currently in this phase · ~3708 volunteer seats required network-wide for this phase alone

P5 — Permanent power, charge & swap fit-out

Weeks 33–40

Deliverables: Permanent distribution, Charge posts, Battery cage, Commissioning certificates

RolePer station (contract)Network demand now*
Power Systems Technician 3 927
Battery Swap Specialist 2 618
Charge Technician 2 618
Site Engineer (Pad & Structures) 1 309

* 309 contracts currently in this phase · ~2472 volunteer seats required network-wide for this phase alone

P6 — Finishes, signage & dual-use optimisation

Weeks 41–46

Deliverables: Wayfinding, Customer desk, Lighting, Agri/construction bay marks

RolePer station (contract)Network demand now*
Site Build Volunteer 3 927
Passenger & Pilot Host 2 618
Community & Comms Volunteer 1 309
Agri & Multi-Purpose Ops Support 1 309

* 309 contracts currently in this phase · ~2163 volunteer seats required network-wide for this phase alone

P7 — Snagging, certification & full operations handover

Weeks 47–52

Deliverables: Snag list closed, As-built pack, Ops SOP signed, Station Manager acceptance

RolePer station (contract)Network demand now*
Contract Administrator 1 309
Station Manager 1 309
Operations Lead 1 309
Safety & Anti-Collision Observer 1 309
Revenue & Records Clerk 1 309
HSE Build Officer 1 309

* 309 contracts currently in this phase · ~1854 volunteer seats required network-wide for this phase alone

How this aligns with the 3-month volunteer program

  • ◆ A 90-day internship covers part of one or two contract phases depending on start date.
  • ◆ Volunteers pick a role required by the active phase at their preferred region (see application form).
  • ◆ Daily timed tasks on the Flyriders dashboard match that role (build + ops roles).
  • ◆ Temporary power phase (P3) is when charge/swap revenue starts while later phases finish the permanent station.
  • ◆ Station Manager / Ops roles peak at handover (P7) as the node goes fully operational.