Angola Hub 16 · Angola · Type: full_service · Design: standard multi-activity node (passenger, agri, construction-capable)

Programme status: Mobilisation & site survey (6%) · in_progress

Every station uses the same multi-activity design. Below are all contracts required for this location to be built and operated: construction, power, structure, batteries, ops labour, general supplies, multi-activity bays, water, food, staff payroll support, utilities, security, medical, waste, insurance, plus the master agreement. Each contract lists payable labour and supplies (including food & water payments).

Build & fit-out

CIVIL — Civil Works & Pad Construction

$43,484.00

Category: construction · Phases: P1, P2

Foundations, primary landing pad, drainage and civil package to support multi-activity use (passenger, agri, construction craft).

Labour (activities)

ItemQtyUnitRateAmount
Site engineer days 40 day $162.00 $6,480.00
General labour (pad & civil) 180 day $47.00 $8,505.00
HSE officer days 30 day $122.00 $3,645.00
Materials coordinator days 25 day $95.00 $2,363.00
Labour subtotal$20,993.00

Supplies & materials

ItemQtyUnitRateAmount
Cement & aggregates 1 lot $11,475.00 $11,475.00
Rebar & mesh 1 lot $5,670.00 $5,670.00
Drainage fittings 1 lot $2,430.00 $2,430.00
Temporary fencing 120 m $24.00 $2,916.00
Supplies subtotal$22,491.00

POWER — Electrical Power — Temporary & Permanent

$49,208.00

Category: electrical · Phases: P3, P5

Temporary charge kits for early ops, then permanent distribution, earth grid and charge posts.

Labour (activities)

ItemQtyUnitRateAmount
Power systems technician days 55 day $149.00 $8,168.00
Charge technician assist days 40 day $88.00 $3,510.00
Commissioning engineer days 12 day $203.00 $2,430.00
Labour subtotal$14,108.00

Supplies & materials

ItemQtyUnitRateAmount
Temporary charge kits 2 set $4,320.00 $8,640.00
Permanent charge posts 4 unit $3,780.00 $15,120.00
Cables, breakers, earth kit 1 lot $8,775.00 $8,775.00
Distribution board 1 unit $2,565.00 $2,565.00
Supplies subtotal$35,100.00

STRUCT — Shelter, Restroom & Services Core

$38,867.00

Category: construction · Phases: P4, P6

Weather shelter, restrooms, store and customer desk so the node supports longer stays and multi-activity turnarounds.

Labour (activities)

ItemQtyUnitRateAmount
Structural labour days 120 day $54.00 $6,480.00
Site engineer days 28 day $162.00 $4,536.00
Finishes & signage labour 35 day $51.00 $1,796.00
Labour subtotal$12,812.00

Supplies & materials

ItemQtyUnitRateAmount
Shelter frame & roofing 1 lot $16,200.00 $16,200.00
Restroom fixtures 1 lot $4,725.00 $4,725.00
Lighting & wayfinding 1 lot $2,970.00 $2,970.00
Furniture (desk, seating) 1 lot $2,160.00 $2,160.00
Supplies subtotal$26,055.00

BATTERY — Battery Swap Cage & Packs Logistics

$30,915.00

Category: equipment · Phases: P5

Secure battery cage, handling gear and initial swap inventory for multi-craft operations.

Labour (activities)

ItemQtyUnitRateAmount
Battery specialist install days 20 day $128.00 $2,565.00
Safety officer days 10 day $122.00 $1,215.00
Labour subtotal$3,780.00

Supplies & materials

ItemQtyUnitRateAmount
Battery cage & fire suppression 1 set $10,125.00 $10,125.00
Handling carts 4 unit $608.00 $2,430.00
Starter swap pack inventory 12 pack $1,215.00 $14,580.00
Supplies subtotal$27,135.00

Operate — staff, food, water & services

LABOUR-OPS — Operations Labour (Build-to-Ops Transition)

$22,141.00

Category: labour · Phases: P3, P6, P7

Standing labour to run limited ops during construction and staff the station through handover — hosts, clerks, safety observers.

Labour (activities)

ItemQtyUnitRateAmount
Ops lead days 45 day $135.00 $6,075.00
Safety observer days 50 day $95.00 $4,725.00
Passenger host days 60 day $61.00 $3,645.00
Revenue clerk days 40 day $74.00 $2,970.00
Station manager handover days 15 day $176.00 $2,633.00
Labour subtotal$20,048.00

Supplies & materials

ItemQtyUnitRateAmount
PPE & radios 1 lot $1,620.00 $1,620.00
Ticketing / log books 1 lot $473.00 $473.00
Supplies subtotal$2,093.00

Other

SUPPLY-GEN — General Supplies & Consumables (12 months)

$7,992.00

Category: supplies · Phases: P3, P5, P7

Ongoing consumables for a multi-activity station: connectors, fluids, cleaning, first aid, signage stock.

Labour (activities)

ItemQtyUnitRateAmount
Stores clerk days 24 day $54.00 $1,296.00
Labour subtotal$1,296.00

Supplies & materials

ItemQtyUnitRateAmount
Charge connectors & spares 1 lot $2,430.00 $2,430.00
Cleaning & sanitation 1 lot $1,215.00 $1,215.00
First-aid & emergency kits 2 set $378.00 $756.00
Office & customer supplies 1 lot $810.00 $810.00
Spare fasteners & tools 1 lot $1,485.00 $1,485.00
Supplies subtotal$6,696.00

MULTI — Multi-Activity Fit-Out (Agri & Construction Bays)

$12,515.00

Category: specialist · Phases: P6

Marked bays, rinse/decontamination zone and heavy-lift windows so one station design supports agri spray and construction lift craft.

Labour (activities)

ItemQtyUnitRateAmount
Agri support specialist days 18 day $101.00 $1,823.00
Marking & barrier labour 12 day $47.00 $567.00
Labour subtotal$2,390.00

Supplies & materials

ItemQtyUnitRateAmount
Bay marking & barriers 1 lot $2,970.00 $2,970.00
Rinse / decontam kit 1 set $5,130.00 $5,130.00
Heavy-lift ground anchors 1 set $2,025.00 $2,025.00
Supplies subtotal$10,125.00

WATER — Water Supply & Sanitation Services

$22,748.00

Category: utilities · Phases: P3, P4, P6, P7

Potable water delivery/storage, sanitation servicing and wastewater handling so staff and passengers can operate the station daily.

Labour (activities)

ItemQtyUnitRateAmount
Water systems attendant days (12 months) 120 day $54.00 $6,480.00
Sanitation service visits 52 visit $115.00 $5,967.00
Labour subtotal$12,447.00

Supplies & materials

ItemQtyUnitRateAmount
Potable water tanks (install) 2 unit $1,620.00 $3,240.00
Bulk water delivery (annual) 400 m3 $11.00 $4,320.00
Water treatment / purification consumables 1 lot $1,215.00 $1,215.00
Sanitation chemicals & consumables 1 lot $878.00 $878.00
Plumbing spare parts stock 1 lot $648.00 $648.00
Supplies subtotal$10,301.00

FOOD — Staff & Visitor Food Provisions Contract

$38,475.00

Category: welfare · Phases: P3, P7

Meals and drinking provisions for staff on shift and basic visitor refreshments during long multi-activity operations.

Labour (activities)

ItemQtyUnitRateAmount
Catering coordinator days 60 day $61.00 $3,645.00
On-site food handler shifts 200 shift $34.00 $6,750.00
Labour subtotal$10,395.00

Supplies & materials

ItemQtyUnitRateAmount
Staff meal packages (annual estimate) 4500 meal $5.00 $21,263.00
Drinking water bottles / dispenser refills 1 lot $2,430.00 $2,430.00
Visitor refreshment stock 1 lot $1,620.00 $1,620.00
Kitchenette equipment 1 set $1,283.00 $1,283.00
Food storage (cooler / dry store) 1 set $1,485.00 $1,485.00
Supplies subtotal$28,080.00

STAFF-OPS — Station Staffing & Payroll Support Contract

$66,683.00

Category: labour · Phases: P3, P5, P7

Paid operational staffing envelope so the station can run once temporary power is live — covers core posts beyond pure volunteer hours.

Labour (activities)

ItemQtyUnitRateAmount
Station Manager (6 months transition) 6 month $2,430.00 $14,580.00
Ops Lead (6 months) 6 month $1,890.00 $11,340.00
Charge / battery technicians (2 posts × 6 mo) 12 month $1,215.00 $14,580.00
Safety officer (6 months) 6 month $1,350.00 $8,100.00
Hosts & clerks (2 posts × 6 mo) 12 month $743.00 $8,910.00
Night / security relief shifts 180 shift $41.00 $7,290.00
Labour subtotal$64,800.00

Supplies & materials

ItemQtyUnitRateAmount
Staff uniforms & ID 15 set $61.00 $911.00
Timekeeping / attendance tools 1 lot $432.00 $432.00
Staff training materials 1 lot $540.00 $540.00
Supplies subtotal$1,883.00

UTIL — Utilities — Power Top-Up, Comms & Data

$20,493.00

Category: utilities · Phases: P3, P5, P7

Grid or generator top-up energy, internet/radio links and data for ops, bookings and anti-collision awareness.

Labour (activities)

ItemQtyUnitRateAmount
Comms technician days 24 day $128.00 $3,078.00
Generator operator days 40 day $68.00 $2,700.00
Labour subtotal$5,778.00

Supplies & materials

ItemQtyUnitRateAmount
Generator fuel (annual contingency) 4000 litre $2.00 $6,480.00
Grid connection / meter fees allowance 1 lot $3,375.00 $3,375.00
Starlink / ISP annual service 1 year $1,620.00 $1,620.00
Radio handsets & base 1 set $2,430.00 $2,430.00
SIM / data bundles 1 lot $810.00 $810.00
Supplies subtotal$14,715.00

SEC — Site Security & Access Control

$35,586.00

Category: operations · Phases: P1, P3, P7

Security labour and equipment to protect craft, batteries, supplies and staff at a dual-use build/ops site.

Labour (activities)

ItemQtyUnitRateAmount
Security guard shifts (12 months) 730 shift $38.00 $27,594.00
Access control admin days 24 day $74.00 $1,782.00
Labour subtotal$29,376.00

Supplies & materials

ItemQtyUnitRateAmount
CCTV starter kit 1 set $2,970.00 $2,970.00
Locks, lights, access badges 1 lot $1,215.00 $1,215.00
Perimeter lighting 1 lot $2,025.00 $2,025.00
Supplies subtotal$6,210.00

MED — Occupational Health & First Response

$7,844.00

Category: welfare · Phases: P1, P7

Medical retainers, first-aid resupply and emergency response readiness for staff and visitors.

Labour (activities)

ItemQtyUnitRateAmount
First-aider training seats 8 person $162.00 $1,296.00
Clinic retainer / standby (annual) 1 year $2,430.00 $2,430.00
Labour subtotal$3,726.00

Supplies & materials

ItemQtyUnitRateAmount
Trauma & first-aid kits 3 set $473.00 $1,418.00
AED (shared regional if applicable) 1 unit $1,890.00 $1,890.00
Annual medical consumables 1 lot $810.00 $810.00
Supplies subtotal$4,118.00

WASTE — Waste, Recycling & Hazardous Materials

$6,696.00

Category: operations · Phases: P3, P6, P7

General waste, recycling and safe handling of battery/chemical waste from charge and agri activities.

Labour (activities)

ItemQtyUnitRateAmount
Waste handler days 48 day $47.00 $2,268.00
Labour subtotal$2,268.00

Supplies & materials

ItemQtyUnitRateAmount
Bins & segregation stations 1 set $945.00 $945.00
Hazardous waste disposal allowance 1 lot $2,970.00 $2,970.00
Spill kits 4 set $128.00 $513.00
Supplies subtotal$4,428.00

INSURE — Insurance & Compliance Retainers

$14,445.00

Category: compliance · Phases: P1, P7

Public liability, equipment and staff-related cover required for legal operation of the station.

Labour (activities)

ItemQtyUnitRateAmount
Compliance clerk days 20 day $81.00 $1,620.00
Labour subtotal$1,620.00

Supplies & materials

ItemQtyUnitRateAmount
Public liability premium (annual estimate) 1 year $6,075.00 $6,075.00
Equipment all-risk allowance 1 year $4,320.00 $4,320.00
Staff accident cover allowance 1 year $2,430.00 $2,430.00
Supplies subtotal$12,825.00

MASTER — Development & Operations Agreement

Umbrella agreement binding all build and operating work packages for this location — construction, utilities, food, water, staffing, security, medical, waste and insurance — through full operational capability.

All work packages (build + operate: water, food, staff, utilities, security, medical, waste, insurance…)$418,092.00
Master admin labour$13,500.00
Permits & documentation supplies$39,164.00
Total estimated package for this station$470,756.00

Labour total $219,337.00 · Supplies total $251,419.00 · Scaled by station type (×1.35)