Station Contract Packages
Each location uses the same multi-activity design and the same set of 15 work-package contracts (build + operate: civil, power, structure, battery, ops labour, supplies, multi-activity, water, food, staffing, utilities, security, medical, waste, insurance) plus master — with full labour and supply line items.
Package contents (identical structure every station):
- ◆ CIVIL — Civil Works & Pad Construction
- ◆ POWER — Electrical Power — Temporary & Permanent
- ◆ STRUCT — Shelter, Restroom & Services Core
- ◆ BATTERY — Battery Swap Cage & Packs Logistics
- ◆ LABOUR-OPS — Operations Labour (Build-to-Ops Transition)
- ◆ SUPPLY-GEN — General Supplies & Consumables (12 months)
- ◆ MULTI — Multi-Activity Fit-Out (Agri & Construction Bays)
- ◆ WATER — Water Supply & Sanitation Services
- ◆ FOOD — Staff & Visitor Food Provisions Contract
- ◆ STAFF-OPS — Station Staffing & Payroll Support Contract
- ◆ UTIL — Utilities — Power Top-Up, Comms & Data
- ◆ SEC — Site Security & Access Control
- ◆ MED — Occupational Health & First Response
- ◆ WASTE — Waste, Recycling & Hazardous Materials
- ◆ INSURE — Insurance & Compliance Retainers
- ◆ MASTER — umbrella development agreement
| Station | Country | Build phase | % | Open full package |
|---|---|---|---|---|
| UK Hub 8 | UK | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| UK Hub 9 | UK | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| UK Hub 10 | UK | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| UK Hub 11 | UK | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| UK Hub 12 | UK | P1 Mobilisation & site survey | 6% | View all contracts → |
| UK Hub 13 | UK | P2 Civil works — pad foundation | 20% | View all contracts → |
| UK Hub 14 | UK | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| UK Hub 15 | UK | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| UK Hub 16 | UK | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| UK Hub 17 | UK | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| UK Hub 18 | UK | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| Spain Hub 1 | Spain | P1 Mobilisation & site survey | 6% | View all contracts → |
| Spain Hub 2 | Spain | P2 Civil works — pad foundation | 20% | View all contracts → |
| Spain Hub 3 | Spain | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| Spain Hub 4 | Spain | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| Spain Hub 5 | Spain | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| Spain Hub 6 | Spain | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| Spain Hub 7 | Spain | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| Spain Hub 8 | Spain | P1 Mobilisation & site survey | 6% | View all contracts → |
| Spain Hub 9 | Spain | P2 Civil works — pad foundation | 20% | View all contracts → |
| Spain Hub 10 | Spain | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| Spain Hub 11 | Spain | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| Spain Hub 12 | Spain | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| Spain Hub 13 | Spain | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| Spain Hub 14 | Spain | P7 Snagging, certification & full operations handover | 91% | View all contracts → |