Station Contract Packages
Each location uses the same multi-activity design and the same set of 15 work-package contracts (build + operate: civil, power, structure, battery, ops labour, supplies, multi-activity, water, food, staffing, utilities, security, medical, waste, insurance) plus master — with full labour and supply line items.
Package contents (identical structure every station):
- ◆ CIVIL — Civil Works & Pad Construction
- ◆ POWER — Electrical Power — Temporary & Permanent
- ◆ STRUCT — Shelter, Restroom & Services Core
- ◆ BATTERY — Battery Swap Cage & Packs Logistics
- ◆ LABOUR-OPS — Operations Labour (Build-to-Ops Transition)
- ◆ SUPPLY-GEN — General Supplies & Consumables (12 months)
- ◆ MULTI — Multi-Activity Fit-Out (Agri & Construction Bays)
- ◆ WATER — Water Supply & Sanitation Services
- ◆ FOOD — Staff & Visitor Food Provisions Contract
- ◆ STAFF-OPS — Station Staffing & Payroll Support Contract
- ◆ UTIL — Utilities — Power Top-Up, Comms & Data
- ◆ SEC — Site Security & Access Control
- ◆ MED — Occupational Health & First Response
- ◆ WASTE — Waste, Recycling & Hazardous Materials
- ◆ INSURE — Insurance & Compliance Retainers
- ◆ MASTER — umbrella development agreement
| Station | Country | Build phase | % | Open full package |
|---|---|---|---|---|
| Somalia Hub 23 | Somalia | P1 Mobilisation & site survey | 6% | View all contracts → |
| Somalia Hub 24 | Somalia | P2 Civil works — pad foundation | 20% | View all contracts → |
| Somalia Hub 25 | Somalia | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| Somalia Hub 26 | Somalia | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| Somalia Hub 27 | Somalia | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| Somalia Hub 28 | Somalia | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| South Africa Hub 1 | South Africa | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| South Africa Hub 2 | South Africa | P1 Mobilisation & site survey | 6% | View all contracts → |
| South Africa Hub 3 | South Africa | P2 Civil works — pad foundation | 20% | View all contracts → |
| South Africa Hub 4 | South Africa | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| South Africa Hub 5 | South Africa | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| South Africa Hub 6 | South Africa | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| South Africa Hub 7 | South Africa | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| South Africa Hub 8 | South Africa | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| South Africa Hub 9 | South Africa | P1 Mobilisation & site survey | 6% | View all contracts → |
| South Africa Hub 10 | South Africa | P2 Civil works — pad foundation | 20% | View all contracts → |
| South Africa Hub 11 | South Africa | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| South Africa Hub 12 | South Africa | P4 Superstructure — shelter & services core | 49% | View all contracts → |
| South Africa Hub 13 | South Africa | P5 Permanent power, charge & swap fit-out | 63% | View all contracts → |
| South Africa Hub 14 | South Africa | P6 Finishes, signage & dual-use optimisation | 77% | View all contracts → |
| South Africa Hub 15 | South Africa | P7 Snagging, certification & full operations handover | 91% | View all contracts → |
| South Africa Hub 16 | South Africa | P1 Mobilisation & site survey | 6% | View all contracts → |
| South Africa Hub 17 | South Africa | P2 Civil works — pad foundation | 20% | View all contracts → |
| South Africa Hub 18 | South Africa | P3 Temporary power & limited ops enablement | 34% | View all contracts → |
| South Africa Hub 19 | South Africa | P4 Superstructure — shelter & services core | 49% | View all contracts → |